PRESENTER CONTROLS. DO NOT ATTACH. These values are derived from authored fictional sources, not observed Cowork results. Scope: two pilot teams / 100 users, not six / 330. Later-phase users: 230. Source tracker: 24 tasks; 8 pilot tasks; 16 later-phase tasks. Baseline pilot: 3/8 Complete (37.5%); T06 Blocked; T02 and T06 overdue (2). After latest update: 4/8 Complete (50%); T07 Blocked; T02 overdue (1). Unfinished pilot gates after update: T02, T04, T07, T08. T08 depends on T02,T04,T06,T07; T06 is now complete, the others are not. Training: 14 October 2026, two calendar days after the unchanged 12 October target. Readiness: On hold - launch gates incomplete. Confirmed launch date: blank. OQ01 approved retention period: blank/unresolved, never 30/90/365 by assumption. T14 and T22 are later-phase issues. Exclude them from pilot blocker and overdue cards. Original tracker must remain unchanged; before/after states belong in generated outputs. The update proves why a 50%-complete pilot can still be on hold. Do not reduce readiness to a percentage. Presentation: exactly six slides including title. All sources cited in notes. Scope and gates must match. Dashboard: filters must work; task drill-down must show source/decision and dependency, not just a colour. Browser form: no fields prefilled, no evidence copied from answer key; stop before Save draft. Show no generated product result as rehearsed until that actual result exists.